Dear Ibrahim Demir, Thanks for your input.
The contract and pumps data sheet is clear in that all hot pumps can go upto 2 API.
The problem is contractor now wants to consider 4 API for individual forces and moments while the remaining equations for moments are 2 API.
Is that acceptable from a code point of view? because he now claims that the code allows that factor of 4.