Hello guys,

This post may be quite old but I hope someone could answer my follow-up question.

Would it still be a good practice to place these 2 pipes on the same trapeze with spring hanger, even though they have different vertical movements? And can we still expect them both to sit on the trapeze during operation even though one of them have much higher vertical movement?

Also, by modeling the trapeze as a rigid element, would it also be correct to connect this rigid element to the +y restraints of the two pipes via cnode?

Than you all on advance.


Edited by leo81457 (02/02/16 12:01 AM)
_________________________