HI ,
I am beginner with caesar II , I need help because I am not sure that my job is safe.
I analyse pipeline leaving on the groud ( oil) and i am using loop each 700 m , when I check the displacement ,caesar gives 100 mm , but during operation the diplacement are more than 2 meters ???
another problem with buried pipeline , can some one tell me why the pipeline go up even it's underground...solt is sand 1 meter depth?
please can someone help me for this case , and normally during construction what we need to known for safety construction.
regards