Hi OG,

I have worked on a project similar to yours. The module was transported on its horiz axis due to its vertical height so we had a number of restraints specifically included to support the pipework during transportation. I checked the the SUS case as you did, WNC but I also did a HYD case with Water Filled Weight as some of the pipework was tested on the module. Connections to equipment were done at site with tie-in spools to remove any unwanted movement at the nozzles. On the jobs I have seen this seems to be standard practice.

Hope this helps.