I have a Pressure relief header to run in a plant.
Problem is time! we need to reduce the analysis time to a minimum.
By experiance, the laterally (45degrees) swept stab-in inlets to the relief headers can usually require re-pads.
So that i can reduce the analysis time, i intend to up the run pipe schedule from sch10s to sch40s hence eliminating the repetative addition of repads.
A engineer here has discounted this by stating it is not possible to weld a sch10s branch to a sch40s header.
I'm no welding engineer, but every stress engineer i have worked with regulally uses this trick to reduce work on the main prv headers.
So my question is: is it within engineering reason to do this??
The header is 12" and the run pipes range from 2"to10"
I've looked at the code (B31.3) and i can't find anything to discount it.
Regards Tim.
oh and my apolagies to the welding Eng's if this is a dumb question.!!