Topic Options
#62827 - 04/23/15 09:59 AM Allowable stress for hydro test in WRC-107, NozzlePro
sam Offline
Member

Registered: 02/25/04
Posts: 643
Loc: Maharastra, India
If I design piping for B31.1 or B31.3 - 2010ed - allowable stress for hydro test is 0.9*Sy & Sy.

When I design WRC-107 or NozzlePro & code is same as above, what are allowable stresses for Pm & Pm+Pl+Qb as per ASME Sec VIII Div-2 ?

Is it OK to have these higher allowable without testing requirements as per Sac VIII Div 2 ?

This I am asking in connection with the use of large bore pipe test blind with cris-cross stiffners.
reg,
Sam
_________________________
_

Top
#62832 - 04/24/15 12:21 AM Re: Allowable stress for hydro test in WRC-107, NozzlePro [Re: sam]
sam Offline
Member

Registered: 02/25/04
Posts: 643
Loc: Maharastra, India
I am clarifying the issue further:

As per ASME SEC-VIII Div 2 2007 clause 4.1.6 Pm < 0.95*Sy & Pm + B < min (1.43*Sy , 2.43*Sy-1.5*Pm)

For hydrotest blind FEA, are the above limits to be followed if Sec VIII Div-1 vessel & B31.1/ B31.3 piping hydrotest ?

Some people are following Nodal stress - von mises max < Sy; is it not too conservative relative to Div 2 basis!

reg,
sam
_________________________
_

Top
#62844 - 04/25/15 08:09 AM Re: Allowable stress for hydro test in WRC-107, NozzlePro [Re: sam]
Dorin Daniel Popescu Offline
Member

Registered: 06/05/00
Posts: 151
Loc: Middle East
Hi,

As a general requirement, you should follow the Project specifications and assigned design Codes requirements.
From your description and questions, I guess your piping design Code is one of the B31 piping Codes (B31.3, 31.1 etc.), and you may have some hydro-test overstress problems with your piping system.

Having this assumption, it should be stated that for all piping components, you have to follow your piping Design Code requirements, regardless you deal with very large bore or common bore pipe size.

You should be aware that B31 piping codes operate with different stress classification and qualification criteria than ASME VIII BPV Code does. Therefore, it is fully speculative to try to increase hydro-test stress allowable limit for B31 piping components because of ASME VIII-2 Section 4.1.6.2 provisions.
Going further with your reasoning, then why not to increase the allowable limit for B31 piping Sustained stresses (fixed at allowable stress Sh) because ASME VIII-2 limits resultant Pl+Pb (primary membrane local + bending stress) at the maximum between Sy and 1.5*Sh ??! (VIII-2, Sections 4.1.6.1 and 5.2.2.4)

So, the fact is you should follow Piping design Code requirements for all piping components. However, you need to use ALL design code provisions and interpretations, and to be aware of Caesar II proper settings facilities.

Hydro-Test load is classified as a primary action and the corresponding failure mode is piping component collapse. During piping system lifetime, hydro-test load is developed only few times, so that hydro-test should not be considered as a cyclic action and fatigue failure is not a characteristic for this load. This is the reason why old CII versions treated hydro-test as Occasional load. However, Hydro-Test load limit state is actually above the typical Occasional piping stress limit state (e.g. Sy > 1.15...1.33 * Sh), so that the reference Hydro-test allowable stress was corrected in accordance with actual B31 design Code provisions (0.9...1 * Sy).

For ASME B31.3 Code editions prior to 2010 edition, the Sustained and Occasional stresses assessment & qualification philosophy was detailed and implemented by B31.3 Interpretation 1-34, which provided that for Sustained and Occasional stresses calculation, only 75% of SIFs (but min. 1.00 values) may be used, OR by interpretation 6-03, which stated that SIFs may be quite omitted for Sustained stress calculation.
Consequently, for Hydro-Test stress computation, using only 75% of SIFs represented a reasonable approach. The reason is that it is unlikely hydro-test load to induce piping components fatigue failure.

ASME B31.3 2010 Edition (which appears you use on your current Project, probably with CII V. 6.10) introduced at Section 320 explicit formulas for Sustained Code stress assessment. These formulas (based upon 75% of SIFs employment) may be extended for Occasional and Hydro-Test stresses computation.
Therefore, be careful and check CII configuration file. Inside “SIF’s and Stresses” menu of Caesar II Configuration File spreadsheet, do you have ”B31.3 Sustained SIF Multiplier” parameter fixed to 0.75 value? Only in this way you'll use reduced SIFs (75%) for Sustained, Occasional and Hydro-Test (probably!) stress computation.

Moreover, you might ignore SIFs employment for non-expansion stresses (especially hydro-test load!) by fixing ”B31.3 Sustained SIF Multiplier” to 0.0001 value. In this way, you'll be in line with B31.3 6-03 interpretation.
However, in my opinion, you'll need to document in Project specifications (design basis) the SIFs omission for Hydro-Test / Occasional / Sustained stress qualification.

If you intend to reduce SIFs for Hydro-Test stresses only, you'll need to perform a separate CII run (with corresponding modified CII configuration setting) for this purpose.

ASME B31.3 2012 Ed. (implemented within CII V. 7.00) uses SSI (Sustained Stress Index) concept for Sustained (and, by extension, Occasional and Hydro-Test) stresses assessment. As per the default B31.3 provisions, the SSIs are somehow equivalent to 0.75% of SIFs approach.

If the above approach still yields to Hydro-Test overstress, then you'll need probably to carry out a detailed local stress analysis by FEA. I guess the overstress occurs at fittings' level (intersections, elbows), so that you may use PRG FEA Software package (FE Pipe, Nozzle Pro) and ASME VIII-2 qualification criteria. You need to "isolate" the fitting by upstream/downstream nodes in CII model, to identify the internal forces & moments in those nodes for Hydro-Test load, and finally to use those loads as boundary limits for the 3D Shell FEA model.
Local stress analysis shall always be based on ASME VIII-2 phylosophy, since the local FEA stress analysis quantifies the stress components of Pm, Pl, Pb, Q, F stress categories, which are not addressed by B31 piping Codes.


Best regards,
_________________________
Dorin Daniel Popescu

Lead Piping Stress Engineer

Top
#62928 - 05/03/15 02:02 AM Re: Allowable stress for hydro test in WRC-107, NozzlePro [Re: sam]
sam Offline
Member

Registered: 02/25/04
Posts: 643
Loc: Maharastra, India
Dear,

"Use of large bore pipe test blind with criss-cross stiffners"- is the area I am referring to.

As a flat plate test blind weld requires more thickness than a circular quadrant as per Roark's formula, by welding criss-cross stiffner members over blind plate I am trying to achieve.

Now, in the FEA or Roark's formula for max stress what will be the allowable stress to compare with - it is not a B31.3 codal stress - so, allowable needs to be as per ASME SEC-VIII Div 2 clause 4.1.6 hydro test load allowables :Pm < 0.95*Sy & Pm + B < min (1.43*Sy , 2.43*Sy-1.5*Pm)!

FE Pipe can simulate flat plate blank; but, till, the allowable stress I need to choose - Isn't it!

FE Pipe is not having any test load input, specifically!

I have presented my argument; is it right or wrong, please tell. I can't consider in FEA hydro test as normal Level A/B primary load!
reg,
sam


Edited by sam (05/03/15 02:07 AM)
_________________________
_

Top
#62929 - 05/03/15 11:11 AM Re: Allowable stress for hydro test in WRC-107, NozzlePro [Re: sam]
Dorin Daniel Popescu Offline
Member

Registered: 06/05/00
Posts: 151
Loc: Middle East
If you have to perform a local stress analysis, you should follow ASME VIII-2 Part 5.

The allowable stresses depends on what categories of stresses you deal with. Section 4.1.6 refers to PRIMARY MEMBRANE Stresses only. If you need to analyze a complex stress state, consisting generally in Pm, Pl, Pb, Q and F stresses (see VIII-2 Figure 5.1), the limits are those described at VIII-2 part 5.

For Hydro-test, you'll have probably Pm or Pl, Pb and Q stresses to consider. Yes, PRG FEA package does not address hydro-test load specifically. But you may consider it as a Primary Occasional Load. So, specify the hydro-test load as Occasional type. You'll get the qualifications for resultant Pl+Pb and Pl+Pb+Q equivalent stresses. My opinion is that Pl+Pb will be qualified conservatively, while for resultant primary+secondary (Pl+Pb+Q) stress you'll get the right result, since the protection against ratcheting is not related to the quasi-permanent or occasional type of the load.

I cannot give other details, since it's unclear for me what you mean by "hydrotest blind FEA" or "flat plate test blind weld". Maybe it's a welded flat cover (or blind flange), with/without orifice, subjected to uniform pressure load. In such case, I think the approach described above it's OK.

Maybe other forum members are more aware about such problems.

Regards,
_________________________
Dorin Daniel Popescu

Lead Piping Stress Engineer

Top
#73431 - 07/10/19 10:09 PM Re: Allowable stress for hydro test in WRC-107, NozzlePro [Re: sam]
sam Offline
Member

Registered: 02/25/04
Posts: 643
Loc: Maharastra, India
What I wrote about test condition load allowable stress in Sec-VIII Div 2:2015 clause 4.1.7 is what we have used for hydrotest of a large number of applications successfully. If we bow to US, it is due to ASME codes, excellent engineering culture which keeps us all safe and sound in logical systematic way!

When you use FEA, know about your loading and corresponding code allowable, too!

In this direction, I depend on FePipe & NozzlePro of PRG as general purpose FEA codes do not provide much direction and help our Tony Paulin could provide in need - I remember, he helped me in pressure design of giant sized WYE joint under high pressure safely by FEPipe.

What Dorin wrote in the above email is really the same.

Keep tight control over the input data - dimensions, material s PMI test, specification and corresponding yield stress at per with Div-2 design by analysis approach.

reg,
sam
_________________________
_

Top



Moderator:  Denny_Thomas, uribejl 
Who's Online
0 registered (), 33 Guests and 2 Spiders online.
Key: Admin, Global Mod, Mod
April
Su M Tu W Th F Sa
1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30
Forum Stats
12065 Members
14 Forums
16973 Topics
75151 Posts

Max Online: 303 @ 01/28/20 11:58 PM
Top Posters (30 Days)