Reports are usually coming late in the project as important is to solve the problems and less important is to have the paper. Some companies have at 30% preliminary stress analysis for the most critical lines, while at 6o% start to perform the stress analysis for all lines subject to stress calculations with the aim to have all completed (finalized) at 90 %. Yet this depend on the organization/company/client/contract.
_________________________
Dan