Dear Richard & Dave,
I am reading COADE book for this water hammer analysis procedure.
I am reading EI guide line for calculating LOF and further actions required.
I have one doubt regarding SMALL BORE LINE CONNECTIONS (SBC), generally for SBC, we will give less preference or even we didn’t take into analysis but In EI guideline, they given a separate assessment for MAIN LINE & SBC also.
My doubt is SBC lines should be included in the CAESAR-II analysis or not.
Please correct me if I am wrong.
_________________________
Thanks,
Durga