Thanks for your replies,
I have in fact C-Nodes before and after the EXJ element, but my question is what is the the value that I should consider ?
The maximum of the two C-Nodes ?
The difference ?
The sum ?
Another question: If I don´t put C-Nodes can I look for the Global Element Forces report ?
And once again should I consider the maximum, the sum or the difference ?
IFPC