#33038 - 02/08/10 10:35 AM Pile Driving Near Buried Pipelines
Andy3568 Offline
Member

Registered: 02/08/10
Posts: 1
Loc: Louisiana
I have been asked to use Caesar II to model a buried pipeline that will be experiencing outside forces due to pile driving near the pipeline. I have used Caesar II extensively to model stresses caused by steady state conditions (thermal expansion, weight, etc.), but I am not very experienced with Caesar II's dynamic capabilities. I don't even know if Caesar II could model this scenario effectively. Any input would be appreciated.
_________________________
Thanks.

Andy Anderson
Petronyx Consulting Engineers, LLC
http://www.petronyx.com

Top
#33044 - 02/08/10 08:25 PM Re: Pile Driving Near Buried Pipelines [Re: Andy3568]
Richard Ay Offline
Member

Registered: 12/13/99
Posts: 6226
Loc: Houston, Texas, USA
How would you describe this load (numerically speaking)?
_________________________
Regards,
Richard Ay - Consultant

Top



Moderator:  Denny_Thomas, uribejl 
Who's Online
0 registered (), 31 Guests and 1 Spider online.
Key: Admin, Global Mod, Mod
May
Su M Tu W Th F Sa
1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31
Forum Stats
12065 Members
14 Forums
16973 Topics
75151 Posts

Max Online: 303 @ 01/28/20 11:58 PM
Top Posters (30 Days)