Try to have your project engineers actually do some work and get a copy of "Factories Act (Chapter 104), Section 42)." Basically for all steam piping in Singapore. Some systems will require "local review/approval" and of course a nice report will need to be prepared per their rules.
This is just one requirement I know about. There could be more.