Posted by: MGR
buried pipe modeling - 02/26/08 04:58 AM
Dear ALL..
how u all,,hope all enjoyinng..\
i have a doubt regarding the modelling for the pipe buried underground,,,
i seen the Coade seminar notes and there it is mentioned that for the modeeling the pipe above 12" dia we have to maintain the nodes distance every 20D. Now the quest is it mandatory to follow this?
Else can i model the straight 300 mtrs without maintaining the 20D distance ..will thr be any effeects ..
Hope to get reply fast..
Thanks
how u all,,hope all enjoyinng..\
i have a doubt regarding the modelling for the pipe buried underground,,,
i seen the Coade seminar notes and there it is mentioned that for the modeeling the pipe above 12" dia we have to maintain the nodes distance every 20D. Now the quest is it mandatory to follow this?
Else can i model the straight 300 mtrs without maintaining the 20D distance ..will thr be any effeects ..
Hope to get reply fast..
Thanks