Hi MoverZ
- There are bellows existing in the line already (to take the platform relative movements) and the piping at the entry to the bridge is not entirely exposed.
- The existing piping is designed (routing/supports) to take the differential movements of the platform. The bridge has the fixed end at the right side of the sketch. before the expansion bellow(pipe flow left to right)and after the pipe is guided, so I don't expect any lateral movement at the expansion bellow (new)
- regarding flex hose. The line is 12" and flex hoses are available only upto 8" and the requirement is to keep the work in the bridge piping to a minimum. at the other end outside the bridge the piping has 2x 8" branches
- There are 2 No.s of firewater lines and the flex hoses are used to keep one operating while the other is hard piped (after the bridge lift)
_________________________
SN