Why is it that a teflon slide plate is required b/w the load flange of the base spring and the pipe attachment when the resultant horizontal movement on the pipe is greater than 1/4"? Thanks in advance....
Registered: 04/21/01
Posts: 62
Loc: India, Australia(Perth)
This requirement is basically to avoid the Load Flange Column from getting jammed with the casing ,,due to the Friction force generated by the Sliding Support component or pipe.