If Power plant has to be build in process Refinery then where specification break between B31.1 & B31.3??

plz clarify .i am confused about this question
_________________________
Anand
'Stress should be in Pipe not in Life'

Top
#59073 - 05/19/14 10:51 PM Re: Code confusion [Re: anand1541991]
anand1541991 Offline
Member

Registered: 01/08/14
Posts: 14
Loc: india
Can any one just help to sort it out.
_________________________
Anand
'Stress should be in Pipe not in Life'

Top
#59091 - 05/21/14 12:42 AM Re: Code confusion [Re: anand1541991]
mariog Offline
Member

Registered: 09/29/07
Posts: 798
Loc: Romania
The power boilers must be in accordance with BPV Code Section I and associated sections of BPV.

Boiler external piping is required to conform to B31.1.

IMO, for your case, Non-boiler External Piping can be either B31.1 or B31.3, depending on the costs vs. benefits your Client wants to assign to.

See B31.1/ B31.3 "Scope and Definitions" chapters.

Top



Moderator:  Denny_Thomas, uribejl 
Who's Online
0 registered (), 34 Guests and 2 Spiders online.
Key: Admin, Global Mod, Mod
May
Su M Tu W Th F Sa
1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31
Forum Stats
12065 Members
14 Forums
16973 Topics
75151 Posts

Max Online: 303 @ 01/28/20 11:58 PM
Top Posters (30 Days)