Hi ,

such a line under decoking process , for the case of disassembly how temporary supports can be provided in vertical displacement of operating -9mm and for sustain -19 mm ? In sustained spring can not take the weight of pipe when it's disassembled and pipe is trying to go down.

On equipment connections can we allow pipe to create a deflection more than 13mm. when pipe is disassembled ?

Thanks..


Top
#31905 - 12/10/09 07:51 AM Re: Temporary support for decoke [Re: Stealth]
MoverZ Offline
Member

Registered: 11/22/06
Posts: 1195
Loc: Hants, UK
You should aim to install temporary supports such that the pipe remains exactly where you want it to be, and remains there in a safe condition. It may need horizontal restraint in addition to temp. weight support.

I'm not sure what you are asking regarding equipment connections.

Top



Moderator:  Denny_Thomas, uribejl 
Who's Online
0 registered (), 40 Guests and 1 Spider online.
Key: Admin, Global Mod, Mod
April
Su M Tu W Th F Sa
1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30
Forum Stats
12065 Members
14 Forums
16973 Topics
75151 Posts

Max Online: 303 @ 01/28/20 11:58 PM
Top Posters (30 Days)